pmstudio-dr
Generate a Disaster Recovery plan with RTO/RPO targets. Use when someone asks to "create a DR plan", "disaster recovery", "business continuity", or "RTO RPO". Do NOT use for step-by-step restoration runbooks — use /pmstudio-recovery instead. Designed for SaaS platform products wh
What it does
DR Plan — Disaster Recovery Plan
Purpose
Generates a Disaster Recovery plan scoped to a specific product. For SaaS products (where the vendor owns infrastructure), this plan focuses on what Coco Inc controls: data exports, integration failover, access recovery, communication, and business continuity.
Process
Step 1: Read Context
Read all that exist:
CLAUDE.local.md— architecture, integrations, vendor info, data strategyPRD/*.htmlorPRD/*.md— NFRs, technical considerations, integrations, data architectureArchitecture/— system diagrams, data flowsOperational/IRP-*.html— incident response plan (if exists, reference for communication)
Step 2: Determine Product Type
From context, classify the product:
| Type | DR Focus | Example |
|---|---|---|
| SaaS (customer) | Vendor dependency, data portability, alternative workflows | (third-party SaaS) |
| Self-hosted | Infrastructure recovery, backup/restore, failover | Custom app on EKS |
| Hybrid | Both vendor and self-hosted components | SaaS + custom middleware |
Adjust the plan scope accordingly. For SaaS, skip infrastructure sections (that's the vendor's problem). Add vendor SLA and data portability sections.
Step 3: Ask Discovery Questions
Only ask what can't be inferred:
- Business criticality tier? (Tier 1 critical / Tier 2 important / Tier 3 standard)
- What's the maximum tolerable downtime? (This becomes RTO)
- What's the maximum tolerable data loss? (This becomes RPO)
- Are there manual workarounds if the product is down? (e.g., "we can use Excel for 48 hours")
- Vendor SLA? (uptime commitment, support response times, data export capabilities)
- Backup strategy? (Does data export to Snowflake/SharePoint? How often?)
Step 4: Generate DR Plan
Output: Operational/DR-Plan-{ProductName}-{Date}.html
Self-contained HTML with clean typography and print CSS.
11 sections:
1. Purpose & Scope
- Product name, ProdID, instances covered
- What this plan covers and doesn't cover
- Relationship to vendor's own DR plan
2. Service Classification
- Business criticality tier with justification
- Data classification (Purple/Red/Yellow/Green)
- Regulatory or compliance requirements affecting recovery
- Business impact of downtime (per hour/day)
3. RTO/RPO Targets
Per-component target table:
| Component | RTO | RPO | Justification |
|---|---|---|---|
| Core platform | 4 hours | 24 hours | Vendor SLA: 99.9% uptime |
| Data in Snowflake | 2 hours | 0 (real-time sync) | Analytics feeds downstream |
| Integrations (SSO) | 1 hour | N/A | Users locked out |
| Integrations (ServiceNow) | 8 hours | N/A | Ticket creation manual fallback |
4. Disaster Scenarios
Ranked by likelihood x impact:
- Vendor platform outage (most likely) — vendor is down, product inaccessible
- Data corruption — bad data entered or sync error corrupts records
- Access loss — SSO failure, license revocation, permission misconfiguration
- Integration failure — upstream/downstream system breaks connection
- Security breach — unauthorized access, data exfiltration
- Vendor business failure — vendor acquired, shut down, or ends product
For each scenario: description, likelihood, impact, detection method.
5. Recovery Procedures
Per-scenario step-by-step. See references/saas-dr-patterns.md for SaaS-specific recovery patterns.
Structure per scenario:
- Trigger condition (how do we know this is happening)
- Immediate actions (first 15 minutes)
- Short-term recovery (first 4 hours)
- Full recovery (to meet RTO)
- Verification checklist
6. Communication Plan
- Who to notify per scenario and severity
- Templates (reference IRP if it exists, or provide standalone)
- Vendor communication (support ticket + account manager)
- Stakeholder updates cadence during outage
7. Dependencies
- External systems required for recovery
- Vendor contacts (support, account manager, escalation)
- SLA commitments and how to invoke them
- Third-party services (SSO provider, email, etc.)
8. Data Backup & Restoration
- What data is backed up (by vendor, by Coco Inc)
- Backup frequency and retention
- Where backups are stored
- Restoration procedure (step-by-step)
- Data validation after restoration
9. Manual Workarounds
- What business processes can continue without the product
- Excel/SharePoint fallback procedures
- Duration the workaround is sustainable
- Data reconciliation procedure when product is restored
10. Testing Schedule
- DR test cadence (annually minimum, semi-annually recommended)
- Test scenarios (tabletop, partial recovery, full recovery)
- Last test date and results
- Next scheduled test
- Test success criteria
11. Review & Maintenance
- Review cadence: semi-annually or after any DR event
- Approval chain (PM, Security POC, Sponsor)
- Version history
- Distribution list
Step 5: Present for Review
Show the plan outline with key decisions highlighted:
- RTO/RPO targets
- Scenario prioritization
- Manual workaround availability
Ask for approval before writing.
Critical Rules
- RTO/RPO must be numbers, not words. "As fast as possible" is not an RTO. Push for specific hours.
- Vendor DR is not your DR. The vendor's uptime SLA is an input to your plan, not a substitute for it. Your plan covers what happens on Coco Inc's side.
- Manual workarounds are critical. For every scenario, document what the business does while the product is down. If there's no workaround, that's a risk to flag.
- Data portability is DR. If you can't get data out of the product, you can't recover from vendor failure. Document export capabilities.
- Test the plan. A plan that's never been tested is a wish list. Include a testing schedule and success criteria.